Page 16 - JUNE 2022
P. 16

Construction Industry


                   CHALLENGES






                                 Pricing and Timing Harder to Forecast


                                                       By Neil Potter




                  enants and landlords are     Market trends in the interior     Real Estate Investment Trusts) are
                  struggling with an environ-  construction division point toward   stockpiling materials (like loading dock
                  ment where construction    higher subcontractor demand due     levelers) making issues even worse.
                  is much more complicated   to latent projects breaking free. We   In conclusion, construction is
        Tthan it was previously.             are seeing a slight rise in overall   much more complicated than it was
        Both pricing and timing are harder to   subcontractor costs, but mainly in   previously. Both pricing and timing
        forecast. Tenants looking for highly   the drywall, acoustical ceiling, and   are harder to forecast.
        customized space need to start the pro-  metals divisions. The market is not
        cess at least four to six months earlier   fully saturated with work and as more   RECENT LEAD TIMES
        than normal, and landlords are leaning   projects come online, one can expect   ▪ Switch Gear – 52 Weeks from
        into pre-built “spec” suites as a solution   costs to rise accordingly.    Approved Submittals
        for smaller tenants.                   Supply chain issues including     ▪Fixtures – 12-24 Weeks
           The construction industry has     metals and carpet remain a challenge.   ▪Generators – 48 Weeks
        faced an impact in several areas due   Lighting, switch gear, doors, and   ▪Doors – 16 weeks
        to pandemic-induced supply chain     appliances also have long lead times.   ▪Ice maker – 32 Weeks
        disruptions. Material procurement has   These issues are continuing to delay   ▪Frames – 3-6 Weeks
        become challenging with the associated   substantial completion of projects   ▪Appliances – 16 Weeks
        cost escalations and availability. Other   beyond their intended dates and should   ▪Carpet – 8-10 Weeks
        specialized components  continue to be   be planned for accordingly.
        sparse with limited options to expedite,   Material and labor quotes are only   COST INCREASES SINCE AUGUST 2021
        which impacts schedules and material   being held for less than a week in some   ▪ Mechanical, Electrical & Plumbing –
        selections. Longer delivery times for   cases versus the 60 to 90 days to which   Increase by roughly 35%
        materials  indicate that ordering prod-  many were accustomed because of the   ▪ Finishes – Increase by roughly
        ucts early in the process will be critical   rapidly changing prices and delivery   15-20%
        in mitigating scheduling issues.     issues. Large players (e.g., Industrial   ▪ Doors, Frames, Hardware – Increase
                                                                                   by 28%
                                                                                 ▪ Insulation/Fireproofing – Increase
          Construction Activity Delivery Timeline
          75,000 SF or Greater                                                     by 15%
                                                                                 ▪ Millwork – Increase by 22%
                         24200 Via Mazzin Way                  1550 on the Green  ▪ Metals – Increase by 35%
                         Southwest Outlier                     CBD
                         September 2022                        March 2024        ▪ Concrete – Increase by 16%
                         80,000 SF                             386,000 SF        ▪ General Conditions – Increase by 23%
                         Realty 1 Partners                     Skanska USA
                                                                                 ▪ Site Work – Increase by 22%
          2022                        2023                       2024            ▪ Earthwork – Increase by 22% N

                                                                                 Neil Potter is a Senior Project
             4411 San Felipe                  9753 Katy Fwy                      Manager and member of the Design
             Post Oak Park                    Katy Fwy
             May 2022                         May 2023                           and Construction Advisory team
             77,189 SF                        186,000 SF                         at Colliers in Houston, Texas. For
             DC Partners                      MetroNational Corporation
                                                                                 further information connect with Mr.
                                                                      SOURCE: CoStar
                                                                                 Potter at Neil.Potter@colliers.com.
        16  NBIZ  ■ June 2022
   11   12   13   14   15   16   17   18